5 Best Practices for Handling Construction Mistakes
- 1: Take Ownership You or your team members messed up. ...
- 2: Thoroughly Document Mistakes Figuring out what caused the error is just as critical as fixing it. ...
- 3: Communicate With the Entire Project Team Mistakes in construction should never be kept under wraps. ...
- 4: Create the Appropriate Repair Schedule Not every construction mistake can be addressed immediately. ...
- 5: Perform Project Risk Assessment ...
Full Answer
Does a contractor have the right to fix a mistake?
Whose right is it to fix mistakes? Many contractors are under the assumption that if a customer finds fault with their work, the contractor has at very least the right to be told about it and come back and fix it, before the customer can bring in someone else at the contractors expense. Au contraire, mes amis.
What happens if a contractor makes a mistake on a light?
For example, if the supplier made a mistake and shipped two light fixtures instead of three, and the contractor has to wait a week to install the third, you may choose to pay them the majority of the final payment but hold back a few hundred dollars until the final light is in and installed.
What should I do if I have problems with my contractor?
As soon as you begin to have problems with the contractor, one of the best things you can do is to reestablish what the plan is going forward, and what time frame it will happen in the time frame in which it will occur. Are the workers who built your addition also trashing the yard?
Do contractors have the right to tell customers when work goes wrong?
Many contractors are under the assumption that if a customer finds fault with their work, the contractor has at very least the right to be told about it and come back and fix it, before the customer can bring in someone else at the contractors expense. Au contraire, mes amis.

What to do if a contractor messes up?
Here's how.Fire the Contractor. Firing your contractor may seem obvious, but it's not an easy step when things go seriously wrong. ... Request a Hearing. ... Hire an Attorney. ... Take Your Case to Small Claims Court. ... File Complaints and Bad Reviews.
How do you tell a contractor they made a mistake?
When you confront your contractor with the mistake, let them tell their side of the story. It would be best if you didn't start blaming people around the construction site, because they will feel hurt, and your project's workflow will change.
What happens when a builder makes a mistake?
If you're out on the site and see something wrong or different than you expected, bring the issue to your general contractor's attention, or your architect. Those are your two primary contacts. If you talk to the sub contractor building the structure, you'll get nowhere—in fact, it might backfire.
Do contractors make mistakes?
But contractors are people, too. They make mistakes. Knowing which pitfalls are the most pervasive is the first step in avoiding them. Let's look at a few common mistakes — as well as their easy fixes — to ensure you're reducing accidents, keeping projects on budget, and hitting deadlines with pinpoint accuracy.
What should you not say to a contractor?
Seven Things to Never Say to a ContractorNever Tell a Contractor They are the Only One Bidding on the Job. ... Don't Tell a Contractor Your Budget. ... Never Ask a Contractor for a Discount if You Pay Upfront. ... Don't Tell a Contractor That You Aren't in A Hurry. ... Do Not Let a Contractor Choose the Materials.More items...
What are my rights for poor workmanship?
It'll depend on what exactly the issue is, but if your builder has breached any of the terms, you're entitled to have repairs or replacements done and any faulty workmanship put right, free of charge. This should happen within a reasonable time and without causing you significant inconvenience.
When mistakes are made on a construction project who pays for the mistake?
Since mistakes are part of the process, the customer pays for the mistake (assuming the cause isn't blatant negligence by the contractor or builder).
How do you hold builder accountable?
The best way to hold cost-plus builders accountable is to go through your budget line-by-line. Ask about the materials, where they're coming from, what's the plan if they're unavailable, and more in that vein. Get specific and ask about what their contingency plans are.
How do I know if my contractor is unhappy?
How to Convey Your Dissatisfaction to Your ContractorSpeak up right away. You must tell your contractor early on that you don't like something. ... Maintain an understanding demeanor. You don't like the work and you're worried you'll offend your contractor. ... Get changes to the project in writing (even if only by email).
Why do contractors not call back?
The truth is, many contractors simply don't bother returning phone calls, making get-to-know-you appointments or following up on an initial conversation. Maybe they're busy with another job at the moment, or they're not in the mood for work on the day you call, and they simply never get back to you.
What can a contractor do to prevent such a mistake in the future?
How to Handle Construction Mistakes?Take Responsibility. Ad. ... Documentation of Construction Mistakes. Determining the cause of the error is essential to prevent the occurrence of the same mistake in the future. ... Communicate with all Construction Staff. ... Set Appropriate Repair Schedule. ... Perform Project Risk Assessment.
Why do contractors want cash?
In the eyes of state and federal tax authorities, this reason is most likely either: To avoid payroll taxes; To help the contractor evade its income tax obligations; and/or, To falsely report your company's expenses in order to reduce its taxable income.
How do you tell your contractor you are not happy?
How to Convey Your Dissatisfaction to Your ContractorSpeak up right away. You must tell your contractor early on that you don't like something. ... Maintain an understanding demeanor. You don't like the work and you're worried you'll offend your contractor. ... Get changes to the project in writing (even if only by email).
When mistakes are made on a construction project who pays for the mistake?
Since mistakes are part of the process, the customer pays for the mistake (assuming the cause isn't blatant negligence by the contractor or builder).
Why do contractors want cash?
In the eyes of state and federal tax authorities, this reason is most likely either: To avoid payroll taxes; To help the contractor evade its income tax obligations; and/or, To falsely report your company's expenses in order to reduce its taxable income.
What are the requirements for obtaining relief from an erroneous bid?
The requirements for obtaining relief from an erroneous bid were established as follows: 1. The mistaken party must be reasonably prompt in giving notice of its error; 2. The party receiving the bid must not have changed its status so significantly that relief or forfeiture will work a hardship on it; 3.
Can a bid error be reformed?
In federal contracting, a bid error can be reformed as long as the low bidder is not displaced by the reformation. Generally, the courts recognize that bidding is a hectic task and that in the final minutes of rushing to prepare a bid, a contractor may make an error in its bid: “Contractors do not work under ideal conditions in the rush to meet ...
How to tell if a contractor is struggling?
Of course, sometimes the problem starts at the top. If you have concerns about the information you’re getting from the contractor, you may want to talk to the men and women doing the work, especially subcontractors. Ask the people doing hands-on work how things are going, and if you hear that they’re not getting paid or that they’re extremely unhappy, that’s a warning sign that your contractor is struggling with cash flow. But before you do this, be aware that talking to subcontractors and asking uncomfortable questions will almost certainly get back to the general contractor.
How to get along with a contractor?
Ideally, you’ll get along with your contractor and they will be motivated to do excellent work both out of pride in their craft and goodwill toward you. But, if the only way you can ensure that your job is done correctly is to hold a threat of poor reviews or slow payment over their head, you should be willing to do so. If things are going very badly, don’t hesitate to contact a legal professional. By the time you get to that point, it’s a good idea to keep a very close eye on the contractor’s work in order to make sure they’re not cutting corners. If you don’t have the training to do that yourself, ask around and see if you have a friend who can help out. Check out the 10 home improvement projects for which you should always hire a pro.
What is a change order in a bathroom remodel?
This is another area where you want to be understanding, up to a point. Change orders occur when the scope of the job changes for one reason or another. If you decide halfway through a bathroom remodel that you want to upgrade from laminate counter tops to granite, naturally that will impact the timeline and price. Or if the demo for that bathroom remodel began and uncovered signs of a massive termite infestation, that’s an issue that likely wasn’t covered in the initial contract. But if the contractor is giving you a hard sell on alternate choices or upgrades, that’s a warning sign.
Why do homeowners use holdbacks?
It’s amazing how fast things can get done when there’s money on the line! And, while holdbacks are often used by homeowners to give leverage over a contractor, they can also be a way to give the contractors a hand.
What are the issues between contractors and homeowners?
The majority of issues between contractors and homeowners boil down to miscommunication and a lack of updates. All too often contractors get wrapped up in the project details and fail to give proper notification of daily progress and setbacks to the homeowners. While it’s best to establish communication from the get-go, ...
What happens if you move the goalposts?
However, if you move the goalposts to give your contractor room to breathe, then amend the original contract to make sure that you still have maximum options in case things go poorly.
What to do when you are in the middle of a project?
If you’re in the middle of a project and considering tweaking the terms of the contract or adjusting milestones, one of the best things you can do to protect your interests is to stipulate that there will be a holdback of final funds until all items are completed to your satisfaction. The more concerns you have about your contractor, the more you should hold back until you are fully satisfied. It’s amazing how fast things can get done when there’s money on the line!
What happens if a contractor finds fault with their work?
Many contractors are under the assumption that if a customer finds fault with their work, the contractor has at very least the right to be told about it and come back and fix it, before the customer can bring in someone else at the contractors expense. Au contraire, mes amis.
Why do contractors have to comply with the same?
Sometimes owners or developers will have a desire to speed up the project, and contractors are often willing to comply with same so long as the parties have agreed upon additional compensation for the contractor adding additional labor power to accelerate the schedule.
Can you repair your own work if you don't have it in writing?
Since customers with failed work tend to be less friendly to the installing contractor, you are far less likely to have the opportunity to repair your own work (and control the cost of the repairs) if you don’t have it in writing.
Can a contractor come back to fix a customer's fault?
The law is, unfortunately, all over the place on this issue, but in almost all cases, a written agreement on the point will. Many contractors are under the assumption that if a customer finds fault with their work, the contractor has at very least the right to be told about it and come back and fix it, before the customer can bring in someone else ...
