AIA Document G704®–2017 is a standard form for recording the date of substantial completion of the work or a designated portion thereof. The contractor prepares a list of items to be completed or corrected following substantial completion, and the architect verifies and amends this list.

What is the difference between AIA Document g702 and G704?

AIA Document G702®S–2017, Application and Certificate for Payment, and G703®S–2017, Continuation Sheet, provide convenient and complete forms on which the subcontractor can apply for payment. G704–2017, Certificate of Substantial Completion

What is included in a G704 agreement?

In G704, the parties agree on the time allowed for completion or correction of outstanding items; the date when the owner will occupy the work or designated portion thereof; and a description of responsibilities for maintenance, heat, utilities, and insurance.

What is AIA g612-2017?

AIA Document G612™-2017 is a questionnaire, drafted to elicit information from the owner regarding the nature of the construction contract. G612-2017, Owner’s Instructions to the Architect Part B AIA Document G612™-2017 is a questionnaire, drafted to elicit information from the owner regarding the nature of the construction contract.

What is a g714 change in construction?

G714–2017, Construction Change Directive AIA Document G714™–2017 is a directive for changes in the Work for use where the owner and contractor have not agreed on proposed changes in the contract sum or contract time. G715–2017, Supplemental Attachment for ACORD Certificate of Insurance 25

Who owns the AIA?

Who owns the AIA emblem?

Is AIA copyrighted?

image

Who signs the AIA G704?

The Owner, Architect, and Contractor should execute AIA Document G704 at their respective signature lines.

What is the difference between AIA A104 and A105?

For projects of a more limited scope, use of AIA Document A104™–2017, Agreement Between Owner and Contractor for a Project of Limited Scope, should be considered. For even smaller projects, consider AIA Document A105™–2017, Agreement Between Owner and Contractor for a Residential or Small Commercial Project.

What is a letter of substantial completion?

Substantial Completion Definition Substantial completion means the project, or a portion of the project, is fit for its intended use. The owner can then occupy and use the property. The owner must also pay the contractor the last portion of the monies owed for that project or portion of the project.

What is a G702 form?

AIA Document G702®–1992, Application and Certificate for Payment, and G703®–1992, Continuation Sheet, provide convenient and complete forms on which the contractor can apply for payment and the architect can certify that payment is due.

What is AIA A104?

AIA A104™–2017 is a stand-alone agreement with its own internal general conditions and is intended for use on construction projects of limited scope and complexity. The AIA A104 replaces AIA Document A107™-2007, Standard Form of Agreement Between Owner and Contractor for a Project of Limited Scope.

What is the difference between A101 and A201?

A101: The standard agreement between an owner and contractor for a project with a fixed-amount or lump-sum payment. A102: An agreement for projects contracted for the cost of work plus a fee. A201: The general terms and conditions for the A101 and A102/A103. B101: The agreement between the owner and the architect.

What is AIA substantial completion?

1 of AIA Document A201 – 2007, General Conditions for the Contract for Construction, defines Substantial Completion as “the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work ...

When would you apply for substantial completion?

Privately-owned construction, it occurs when the contractual conditions for completion of the construction obligations have been met and the owner is able to take possession or assume beneficial use and occupancy of the project.

WHO issues substantial completion?

Who Signs the Certificate of Substantial Completion? If the project owner opts to issue a certificate of substantial completion or the contractor requests one, it is the responsibility of the architect on the project to inspect the site and issue the certificate.

What is the difference between AIA G702 and G703?

The G703 contains all the specific information about the amounts included in the Pay Apps. The additional documents provide proof and support to the claims made in the AIA G702. Additionally, each G703 builds on previous submissions. As a result, the AIA G703 is a precise and complex document with no room for error.

How do I complete AIA G702?

8:209:45How to fill out the AIA G702 Application & Certificate for PaymentYouTubeStart of suggested clipEnd of suggested clipInformation on your aia g702 pay app it's time to sign and send it out the standard documentMoreInformation on your aia g702 pay app it's time to sign and send it out the standard document requires notarization on each pay app so don't sign that pay app until you're in front of a notary. Public.

What does AIA mean in construction?

The American Institute of ArchitectsThe documents produced by The American Institute of Architects (AIA) are the most widely used standard form contracts in the construction industry.

How is substantial completion determined?

The California Legal Definition of “Substantial Completion” Occupation or use by the owner after the labor has been completed; 60 days after all labor on the project has ceased; or. As soon as all work on the project has completely ceased for at least 30 days and a notice of cessation is filed.

What does it mean by substantially completed?

What constitutes substantial completion of the Work? There is substantial completion when the Contractor completes ninety five percent (95%) of the Work, provided that the remaining work and the performance of the work necessary to complete the Work shall not prevent the normal use of the completed portion.

What does substantial mean in a contract?

substantial performance. n. in the law of contracts, fulfillment of the obligations agreed to in a contract, with only slight variances from the exact terms and/or unimportant omissions or minor defects.

What is Substantial Performance certificate?

Substantial Performance Certificate means a certificate issued by the Contractor or Sub-Contractor certifying the Work under the Contract or Sub- Contractor to have been substantially performed as defined under the Builders Lien Act.

Who owns the AIA?

AIA, The American Institute of Architects and the AIA emblem are registered trademarks owned by the American Institute of Architects. Published/Edition: 2000 ISBN/Book No.: G704.

Who owns the AIA emblem?

AIA, The American Institute of Architects and the AIA emblem are registered trademarks owned by the American Institute of Architects.

Is AIA copyrighted?

AIA Contract Documents and the content therein are copyrighted works owned by American Institute of Architects. AIA Contract Documents are protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction, display or distribution of an AIA Contract Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. AIA Contract Documents are licensed for one time use only and may not be reproduced prior to its completion.

Synopsis

AIA Document G704–2017 is a standard form for recording the date of substantial completion of the work or a designated portion thereof. The contractor prepares a list of items to be completed or corrected following substantial completion, and the architect verifies and amends this list.

Purpose

AIA Document G704™ was developed to establish the date of Substantial Completion for the purpose of commencement of applicable warranties and to allow the Owner to occupy or utilize the Work or designated portion thereof.

Related documents

This document was prepared for use under the terms of AIA Document A201®, General Conditions of the Contract for Construction; and under the general conditions contained in AIA Documents A104™ and A105™.

Changes to the previous edition

G704-2017 includes a revised information block to identify the Project, Contract, Owner, Architect, Contractor, and information relevant to the Certificate of Substantial Completion.

What is the purpose of the AIA document G704?

AIA Document G704™ was developed to establish the date of Substantial Completion for the purpose of commencement of applicable warranties and to allow the Owner to occupy or utilize the Work or designated portion thereof.

What is the G704-2017?

G704-2017 includes a revised information block to identify the Project, Contract, Owner, Architect, Contractor, and information relevant to the Certificate of Substantial Completion. G704-2017 was reorganized so the Architect can sign the form, and include the date of Substantial Completion, immediately after the description of the Work the Architect is certifying. Also, the paragraph regarding warranties was updated to clarify that warranties commence on the date of Substantial Completion unless the parties indicate otherwise in this form.

What is the AIA document G701?

AIA Document G701™-2017 is used for implementing changes in the work agreed to by the owner, contractor, and architect.

What is G702CW-2021?

G702CW-2021, Application for Payment for a COW Project without a GMP

What is a B101?

B101–2017, Standard Form of Agreement Between Owner and Architect

What is A110 contract?

This contact is a stand-alone agreement with its own internal general conditions and is intended for use on custom residential construction projects. A110 may be used for custom residential projects where payment is based on either a stipulated sum or the cost of the work plus a fee, with or without a guaranteed maximum price.

What is the basis of A102?

A102–2017, Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price

What is A101-2017?

A101–2017, Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

What is the basis of payment in A103?

A103–2017, Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work Plus a Fee without a Guaranteed Maximum Price

Who owns the AIA?

AIA, The American Institute of Architects and the AIA emblem are registered trademarks owned by the American Institute of Architects. Published/Edition: 2000 ISBN/Book No.: G704.

Who owns the AIA emblem?

AIA, The American Institute of Architects and the AIA emblem are registered trademarks owned by the American Institute of Architects.

Is AIA copyrighted?

AIA Contract Documents and the content therein are copyrighted works owned by American Institute of Architects. AIA Contract Documents are protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction, display or distribution of an AIA Contract Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. AIA Contract Documents are licensed for one time use only and may not be reproduced prior to its completion.

image

1.Instructions: G704™–2017, Certificate of Substantial …

Url:https://acdoperations.zendesk.com/hc/en-us/articles/1500009322461-Instructions-G704-2017-Certificate-of-Substantial-Completion

10 hours ago AIA Document G704®–2017 is a standard form for recording the date of substantial completion of the work or a designated portion thereof. The contractor prepares a list of items to be …

2.Videos of What Is AIA G704

Url:/videos/search?q=what+is+aia+g704&qpvt=what+is+aia+g704&FORM=VDRE

35 hours ago AIA Document G704®–2017 is a standard form for recording the date of substantial completion of the work or a designated portion thereof. The contractor prepares a list of items to be …

3.G704–2017, Certificate of Substantial Completion …

Url:https://store.aia.org/products/g704-2017-certificate-of-substantial-completion-revised-50-pack

3 hours ago AIA Document G704™–2000 is a standard form for recording the date of substantial completion of the work or a designated portion thereof. The contractor prepares a list of items to be …

4.G704–2000, Certificate of Substantial Completion - AIA …

Url:https://www.aiabookstore.com/g7042000-certificate-of-substantial-completion.html

13 hours ago G704–2000, Certificate of Substantial Completion. AIA Document G704™–2000 is a standard form for recording the date of substantialcompletion of the work or a designated portion …

5.AIA G704 - Certificate of Substantial Completion …

Url:https://www.buildersbook.com/aia-g704-certificate-of-substantial-completion-package-of-50.html

30 hours ago  · AIA Document G704–2017 is a standard form for recording the date of substantial completion of the work or a designated portion thereof. The contractor prepares a list of items …

6.Summary: G704™–2017, Certificate of Substantial …

Url:https://acdoperations.zendesk.com/hc/en-us/articles/1500009430502-Summary-G704-2017-Certificate-of-Substantial-Completion

2 hours ago AIA Document G704™ was developed to establish the date of Substantial Completion for the purpose of commencement of applicable warranties and to allow the Owner to occupy or …

7.Document G704™ – 2017 Instructions - AIA

Url:https://content.aia.org/sites/default/files/2017-10/G704-2017_Instr_080217.pdf

15 hours ago G704–2017, Certificate of Substantial Completion. AIA Document G704®–2017 is a standard form for recording the date of substantial completion of the work or a designated portion …

8.List of all current AIA Contract Documents - AIA

Url:https://www.aia.org/resources/6150803-list-of-all-current-aia-contract-documents

31 hours ago Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible …

9.Document G704 – 2017 - AIA

Url:https://content.aia.org/sites/default/files/2017-10/G704-2017.Sample.pdf

29 hours ago law. Purchasers are permitted to reproduce ten (10) copies of this document when completed. To report copyright violations of AIA Contract Documents, e-mail The American Institute of …

10.Document G704 – 2017 - AIA

Url:https://content.aia.org/sites/default/files/2017-10/G704-2017_090517.pdf

26 hours ago

A B C D E F G H I J K L M N O P Q R S T U V W X Y Z 1 2 3 4 5 6 7 8 9