
What are the crucial benefits of Earned Value Management?
What are the crucial Benefits of Earned Value Management?
- Helps in realistic project planning:
- Gain real-time visibility of centralized information
- Measure schedule and budget accuracies
- Anticipate risks and intervene early
- Enhances accountability and motivation
Why use Earned Value Management (EVM)?
Earned Value Management (EVM) is a systematic project management process which helps managers to measure project performance. EVM is a technique that is used to track the performance of a project against the project baseline and is very effective assuming the project baseline has been accurately calculated.
How to make earned value work on your project?
These are the key requirements:
- Solid schedule and budget estimate: The EVM tells you how your project is performing with respect to your original project plan and budget. ...
- Availability of actual cost data: This is obvious. ...
- Cost planning on a highly granular level: This requirement is the hardest to meet. ...
What does earned value management measure?
Essential features of any EVM implementation include:
- A project plan that identifies work to be accomplished
- A valuation of planned work, called planned value (PV) or budgeted cost of work scheduled (BCWS)
- Pre-defined "earning rules" (also called metrics) to quantify the accomplishment of work, called earned value (EV) or budgeted cost of work performed (BCWP)
What is Earned Value Management and why is it important?
EVM helps provide the basis to assess work progress against a baseline plan, relates technical, time and cost performance, provides data for pro-active management action and provides managers with a summary of effective decision making.
What is meant by Earned Value Management?
Earned Value Management (EVM) is a project performance management methodology that integrates cost, schedule, technical scope, and risk to assess progress against a baseline, use that information to identify problems, and forecast cost (and, to a certain extent, schedule) at completion.
What is Earned Value Management example?
Simply put, it's a quick way to tell if you're behind schedule or over budget on your project. You can calculate the EV of a project by multiplying the percentage complete by the total project budget. For example, let's say you're 60% done, and your project budget is $100,000 — your earned value is then $60,000.
What is the meaning of earned value?
Earned Value (EV) is the percent of the total budget actually completed at a point in time. This is also known as the budgeted cost of work performed (BCWP).
What are the top three 3 EVM performance measures?
EVM is built on three metrics: Planned value, earned value, and actual cost. Think of these metrics in terms of your project budget and schedule.
What are the 3 earned value methods?
Unlike traditional management, in the Earned Value Method there are three data sources: Planned value – PV; Actual value – AV; the earned value of the concrete work already completed.
What are earned value techniques?
Earned Value Technique is an excellent way to track the Project Progress against the Project Plan. It's a method of objectively measuring project performance against the Project baseline. Result from an Earned Value analysis indicates deviation of the Project from cost and schedule baselines.
What are the disadvantages of earned value management?
Numbers don't tell you the whole story and you need a bit of contextual narrative too. Data has to be accurate otherwise you're making assumptions and predictions based on what isn't truly happening. Quality has to be assumed because EV doesn't factor in quality as part of the way it measures performance.
How do you find earned value?
The Formula for Earned Value (EV) Take the actual percentage of the completed work and multiply it by the project budget and you will get the Earned Value. Earned Value = % of completed work X BAC (Budget at Completion).
What is another term for earned value?
Earned Value is also called Budgeted Cost of Work Performed (BCWP). Planned Value (PV) is determined by the cost and schedule baseline. Actual Cost (AC) is determined by the actual cost incurred on the project. Earned Value (EV) tells you, in physical terms, what the project accomplished.
How does EVM impact project quality?
EVM metrics are reliable. The metrics combine three dimensions of a project's performance - scope, schedule and cost - into unified performance measures, which differentiates them from other performance measurement methods and proves them to be realistic and accurate.
How is earned value management implemented?
Implementing Earned Value Management in a Design ConsultancyEstablish a project work breakdown structure. ... Establish a project schedule. ... Calculate and baseline Planned Revenue. ... Track Earned Revenue and Actual Effort. ... Track project performance and adjust Earned Revenue.
How do you use earned value management?
The 8 Steps to Earned Value AnalysisDetermine the percent complete of each task.Determine Planned Value (PV).Determine Earned Value (EV).Obtain Actual Cost (AC).Calculate Schedule Variance (SV).Calculate Cost Variance (CV).Calculate Other Status Indicators (SPI, CPI, EAC, ETC, and TCPI)Compile Results.
What is the value management?
Value Management is concerned with the creation of sustainable value, either at project, product, process, organisational or social level. It is concerned with improving and sustaining a desirable balance between the needs and wants of stakeholders and the resources needed to satisfy them.
What is earned value management in government contracts?
The U.S. Department of Energy (DOE) uses Earned Value Management (EVM) as a performance management tool that measures actual performance of work scope and the associated cost and schedule compared to the approved baseline plan for a project or contract.
What is earned value and how is it calculated?
It's the relationship between the budget and the percentage of completion of a project. It is a method used to calculate the health and status of any project by taking time and cost into consideration. Earned value can be computed this way : Eearned Value = Percent complete (actual) x Task Budget.
What is earned value?
Oftentimes the term “earned value” is defined as the “budgeted cost of worked performed” or BCWP. This budgeted cost of work performed measure enables the project manager to compute performance indices or burn rates for cost and schedule performance, which provides information on how well the project is doing or performing relative to its original plans. These indices, when applied to future work, allow for to project manager to forecast how the project will do in the future, assuming the burn rates will not fluctuate, which oftentimes is a large assumption.
What is Earned Value Analysis?
Earned Value Analysis (EVA) is a method that allows the project manager to measure the amount of work actually performed on a project beyond the basic review of cost and schedule reports. EVA provides a method that permits the project to be measured by progress achieved. The project manager is then able, using the progress measured, to forecast a project’s total cost and date of completion, based on trend analysis or application of the project’s “burn rate”. This method relies on a key measure known as the project’s earned value.
What is cost variance?
The cost variance is defined as the “difference between earned value and actual costs. (CV = EV – AC)” (PMI, 2004, p. 357) Sometimes this formula is expressed as the difference between budgeted cost of work performed and actual cost work performed. If the variance is equal to 0, the project is on budget. If a negative variance is determined, the project is over budget and if the variance is positive the project is under budget.
What can be done with EVMS?
Another analysis that can be done by using EVMS is that of Performance or establishing the project’s burn rate. Two examination of performance are available to the project manager, Schedule Performance Index (SPI) and Cost Performance Index (CPI).
What is the purpose of the Planned Value?
Planned Value describes how far along project work is supposed to be at any given point in the project schedule and cost estimate. Cost and Schedule baseline refers to the physical work scheduled and the approved budget to accomplish the scheduled work. Together, they result in an important value: Planned Value (PV). PV can be looked at in two ways: cumulative and current.
What is EV in project reporting?
EV is the quantification of the “worth” of the work done to date. In other words, EV tells you, in physical terms, what the project has accomplished.
What is EVA in project management?
Earned Value Analysis (EVA) is a method that allows the project manager to measure the amount of work actually performed on a project beyond the basic review of cost and schedule reports . EVA provides a method that permits the project to be measured by progress achieved.
What is earned value management system?
Answer: Earned Value Management System means the process, procedures, tools, and templates used by a company to perform earned value management.
Why is earned value not used?
Answer: Usually it is not used due to a lack of understanding of how important it can be for project risk analysis and forecasting. Earned Value needs time to set-up the system and also can generate the necessity of rethinking how performance and success are measured.
What are the benefits of EVM?
Some of the Contractor benefits are: EVM creates a performance framework. It can help to provide solid risk management. It helps to measure the progress of the project and if we are selecting the stages of the project it can be a very helpful tool.
Can EVM be used for small parts of a project?
Not only for the whole project, EVM can be used for small parts of the project also.
What is earned value management?
In a single integrated system, earned value management is able to provide accurate forecasts of project performance problems, which is an important contribution for project management.
What is EVM in project management?
EVM emerged as a financial analysis specialty in United States Government programs in the 1960s, but it has since become a significant branch of project management and cost engineering. Project management research investigating the contribution of EVM to project success suggests a moderately strong positive relationship. Implementations of EVM can be scaled to fit projects of all sizes and complexities.
What is EVM in manufacturing?
The genesis of EVM occurred in industrial manufacturing at the turn of the 20th century, based largely on the principle of "earned time" popularized by Frank and Lillian Gilbreth, but the concept took root in the United States Department of Defense in the 1960s. The original concept was called PERT/COST, but it was considered overly burdensome (not very adaptable) by contractors whom were mandated to use it, and many variations of it began to proliferate among various procurement programs. In 1967, the DoD established a criterion-based approach, using a set of 35 criteria, called the Cost/Schedule Control Systems Criteria (C/SCSC). In the 1970s and early 1980s, a subculture of C/SCSC analysis grew, but the technique was often ignored or even actively resisted by project managers in both government and industry. C/SCSC was often considered a financial control tool that could be delegated to analytical specialists.
Why was the EVM canceled?
In 1991, Secretary of Defense Dick Cheney canceled the Navy A-12 Avenger II Program because of performance problems detected by EVM.
When was EVM introduced?
In 1979 , EVM was introduced to the architecture and engineering industry in a "Public Works Magazine" article by David Burstein, a project manager with a national engineering firm. This technique has been taught ever since as part of the project management training program presented by PSMJ Resources, an international training and consulting firm that specializes in the engineering and architecture industry.
What is PV in EVM?
The second step is to assign a value, called planned value (PV), to each work package. For large projects, PV is almost always an allocation of the total project budget, and may be in units of currency (e.g. dollar, euro or naira) or in labor hours, or both. However, in very simple projects, each activity may be assigned a weighted “point value" which might not be a budget number. Assigning weighted values and achieving consensus on all PV quantities yields an important benefit of EVM, because it exposes misunderstandings and miscommunications about the scope of the project, and resolving these differences should always occur as early as possible. Some terminal elements can not be known (planned) in great detail in advance, and that is expected, because they can be further refined at a later time.
What is PV in project?
For large projects, PV is almost always an allocation of the total project budget, and may be in units of currency ( e.g. dollar, euro or naira) or in labor hours, or both. However, in very simple projects, each activity may be assigned a weighted “point value" which might not be a budget number.
What is EVM in project management?
Earned value management (EVM) is a systematic process used to measure project performance at various times throughout a project life cycle. EVM helps project managers to determine whether a project is over or under budget, or if the project is on schedule. Project managers can also use EVM to compare the actual work performed to the work ...
What can a project manager use EVM for?
Project managers can also use EVM to compare the actual work performed to the work that was originally planned for the project at a specific period, and to forecast project performance. Let's examine some of the primary elements of earned value management measurements and apply the EVM formulas in the example below. Lesson.
What can Jane use to determine schedule and cost variance?
Jane can use the foundational calculations to determine schedule and cost variance, and the schedule and cost performance indexes.
Can Jane calculate the estimate at completion?
Assuming the remaining work is produced at the planned budget for each widget, Jane can now calculate the estimate at completion for each project team.
What is earned value management?
Earned value management facilitates and simplifies communications on project performance, making it an extremely useful methodology for customers and contractors alike. The three metrics of planned value, earned value, and actual cost allow for simple yet accurate assessments of cost and schedule performance, which enable better project management overall.
What are the components of an earned value management system?
An earned value management system usually comprises four distinct - yet integrated - components: scheduling engine, the cost engine, the reporting engine, and the accounting system.
What is EVM in project management?
Earned value management (EVM) is a project management technique that helps integrate the three related components of project performance: scope, schedule, and cost. The technique is based on the concept of assigning and earning value (the budgeted cost for project activities). Each set of project activities is assigned a value, which is the portion of the project budget allocated for that set of activities. When a set of related project activities is successfully completed, that portion of the project’s value is considered earned.
What are the levels of EVM?
Varying levels of EVM implementation can be broadly classified as simple, intermediate, and advanced implementations. Determining the appropriate implementation is usually a function of the project’s total value, its goals and specifications, and the skill of the project manager and project team.
What is the simplest earning rule?
The simplest earning rule is the 0/100 rule, where a task earns 100 percent of its value upon completion, and no value prior to completion. Depending on the size of a task, however, you can also employ an alternative called the 50/50 rule.
What is actual cost?
Actual cost is the amount of money spent on earning a certain amount of value. When a project’s earned value equals its planned value, it has successfully delivered its scope requirements. Therefore, comparing planned value to earned value allows a project manager to assess whether a project is running according to schedule.
How does earned value management help with scope creep?
Secondly, earned value management can help counteract scope creep. The methodology is based on integrating the three aspects of project performance: scope, cost, and schedule (the latter two being dependent on the scope). The basic principle that all project work must be assigned value serves as a check on scope creep, since strong practice dictates you must reflect all increases in scope by increases in the total value of the project.

Three Crucial Metrics of EVM
- EVM concept is based on three crucial metrics – Planned Value (PV), Earned Value (EV) as well as Actual Cost (AC).
EVM Calculation– Variance Analysis and Performance Index
- The following indicators are required to describe project performance and cost schedule with EVM. Once the values of three crucial metrics are established, analysis of variance and performance index can be performed. There are two plain expressions of variance- schedule variance, cost variance.
Drawbacks of EVM
- EVM has certain drawbacks that cannot be avoided. EVM can be implemented to manage and control the project, but it cannot ensure to solve everything. EVM does not have any tool to show customer satisfaction and the quality of the project. A project’s success never always depends on completion in scheduled time and budget. If the product or service quality is poor and customer…
Recommended Articles
- This is a guide to the Earned Value Management System. Here we discuss the Three Crucial Metrics of EVM, which includes Planned Value (PV), Earned Value (EV), as well as Actual Cost (AC), along with the Variance Analysis and Performance Index. You may also look at the following articles to learn more– 1. Communication Management Plan 2. Scope for Management 3. Proje…
Summary
Overview
- Earned Value Analysis (EVA) is a method that allows the project manager to measure the amount of work actually performed on a project beyond the basic review of cost and schedule reports. EVA provides a method that permits the project to be measured by progress achieved. The project manager is then able, using the progress measured, to forecast a p...
History
Project tracking
Earned value management (EVM), earned value project management, or earned value performance management (EVPM) is a project management technique for measuring project performance and progress in an objective manner.
Earned value (EV)
Earned value management is a project management technique for measuring project performance and progress. It has the ability to combine measurements of the project management triangle: scope, time, and costs.
In a single integrated system, earned value management is able to provide accurate forecasts of project performance problems, which is an important contribution for project management.
Scaling EVM from simple to advanced implementations
EVM emerged as a financial analysis specialty in United States Government programs in the 1960s, with the government specifying rules for contractors must implement an EVM system (EVMS ). It has since become a significant branch of project management and cost engineering. Project management research investigating the contribution of EVM to project success suggests a moderately strong positive relationship. Implementations of EVM can be scaled to fit projects o…
Simple implementations (emphasizing only technical performance)
It is helpful to see an example of project tracking that does not include earned value performance management. Consider a project that has been planned in detail, including a time-phased spend plan for all elements of work. Figure 1 shows the cumulative budget (cost) for this project as a function of time (the blue line, labeled PV). It also shows the cumulative actual cost of the project (red line, labeled AC) through week 8. To those unfamiliar with EVM, it might appear that this pro…
Making earned value schedule metrics concordant with the CPM schedule
EV is calculated by multiplying %complete of each task (completed or in progress) by its planned value
Figure 2 shows the EV curve (in green) along with the PV curve from Figure 1. The chart indicates that technical performance (i.e. progress) started more rapidly than planned, but slowed significantly and fell behind schedule at week 7 and 8. This chart illustrates the schedule perfor…
Earned Value Management Scenario
The foundational principle of EVM, mentioned above, does not depend on the size or complexity of the project. However, the implementations of EVM can vary significantly depending on the circumstances. In many cases, organizations establish an all-or-nothing threshold; projects above the threshold require a full-featured (complex) EVM system and projects below the threshold are exempted. Another approach that is gaining favor is to scale EVM implementation according to t…
Primary EVM Element Calculations
There are many more small and simple projects than there are large and complex ones, yet historically only the largest and most complex have enjoyed the benefits of EVM. Still, lightweight implementations of EVM are achievable by any person who has basic spreadsheet skills. In fact, spreadsheet implementations are an excellent way to learn basic EVM skills.
The first step is to define the work. This is typically done in a hierarchical arrangement called a w…
Schedule/Cost Variance and Performance Index Calculations
The actual critical path is ultimately the determining factor of every project's duration. Because earned value schedule metrics take no account of critical path data, big budget activities that are not on the critical path have the potential to dwarf the impact of performing small budget critical path activities. This can lead to "gaming" the SV and Schedule Performance Index or SPI metrics by ignoring critical path activities in favor of big-budget activities that may have much float. Thi…
Performance Index Details
- Jane is a project manager for a company that produces two special widgets each year for suppliers around the world. Jane receives a project schedule of 10 months and a budget with estimates of what it will cost to produce both widgets (shown below). The project requires 200 widgets to be produced per month for Widget A, and 100 widgets to be produced per month for …