Knowledge Builders

what is etc estimate

by Misty Bailey Sr. Published 3 years ago Updated 2 years ago
image

The Estimate To Complete (usually abbreviated ETC) is the project management measure that shows you the remaining cost you expect to pay in order to complete a project. Note that ETC isn't the final overall expected project budget - this is called Estimate at Completion (EAC).Jul 27, 2021

What is the estimate to complete (etc)?

The Estimate To Complete (usually abbreviated ETC) is the remaining cost you expect to pay in order to complete a project. Note that ETC isn’t the final overall expected project budget - this is called Estimate at Completion (EAC).

What does etc stand for?

Estimate to Complete (ETC) Calculation Methods 1 Bottom-Up Cost Estimation: Here you make a new estimate of the remaining work. 2 ETC Formula: Subtracting the Actual Cost (AC) from Estimate at Completion (EAC) More ...

What is estimate at Completion (EAC)?

Estimate at Completion is equal to the budget, which is the amount of money allocated to complete a project. However, if there are changes to the project, then EAC can be calculated by adding all the estimated costs for the tasks. If the budget of a project changes, then a change order needs to be created and approved.

How to calculate the etc of a project?

The ETC can be calculated either for each task or for the whole project. There are two ways to calculate ETC: Budget at Completion (BAC) is the overall budget for the task. Earned Value (EV) is the current progress expressed as a task budget. Cost Performance Index (CPI) is the efficiency level of the project from the budget standpoint.

image

What does ETC mean in budgeting?

Estimate to complete (ETC) is the amount of money needed to finish the project at any point. More to the point, estimate at completion is equal to the budget, which is the amount of money allocated to complete a project.

What does ETC mean in project management?

Estimated time to completeEstimated time to complete is a projection of the time and or effort required to complete a project activity. Estimated time to complete is a value that is expressed in hours of work required to complete a task or project.

What does EAC and ETC mean?

EAC (Estimate at Completion) and ETC (Estimate to Complete) are two important dimensions of Earned Value Management.

How do you estimate the completion of etc?

They are as follows:Formula 1. EAC = AC + Bottom-up ETC. This formula is used when the original estimation is fundamentally flawed. ... Formula 2. EAC =BAC/Cumulative CPI. ... Formula 3. EAC = AC + (BAC - EV) ... Formula 4. EAC = AC + [BAC - EV / (Cumulative CPI x Cumulative SPI)]

How do you calculate EAC and etc?

The formulas to calculate the EAC based on these 4 approaches are: EAC with bottom-up ETC: EAC = AC + ETC. EAC with ETC at budgeted rate: EAC = AC + BAC – EV. EAC with ETC based on present CPI: EAC = BAC / CPI.

What does ETC mean construction?

ETC Project Management Abbreviation4ETCBusiness, Business Planning, Product Development1ETCEstimate, Projection, Management1ETCManagement, NASA, Science

What is EAC estimate at completion?

Estimate at Completion (EAC) is the current expectation of total cost at the end of a project. The EAC represents the final project cost given the costs incurred to date and the expected costs to complete the project.

How is EVM EAC calculated?

The standard EVM EAC equations are:EAC = ACWP + ETC.EAC = BAC / CPI.EAC = AC + (BAC – EV)EAC = ACWP + (BAC – BCWP) / CPI + SPI)

What if EAC is higher than BAC?

If the actual costs at time now (i.e., ACWPcum) are higher than the earned value at time now (i.e., BCWPcum), we know that the contractor is currently over running cost and that the contractor's Estimate at Completion (EAC) may be higher than the BAC.

How do you calculate an estimate?

Estimation uses round numbers in a calculation to make it quicker or easier to get an approximate answer. For example, if we were to estimate the answer to 11.87 x 4.876. We could use the calculation 10 x 5 = 50. This gives us a sensible estimate that we can calculate in our head.

What does a positive EAC mean?

This variance is expressed as EAC variance. A negative EAC variance indicates a project that looks like it is going to come in under the original budget baseline figure. A positive EAC variance indicates that a project is likely to overspend relative to the baseline figure.

How do you estimate project time?

How to estimate project hoursReview project scope. ... Create a list of tasks. ... Collect data for each task. ... Include external hours. ... Consider revision hours. ... Consider adding contingency hours. ... Add all components together. ... Review and revise the estimate.

What does ETC mean in business?

An exchange-traded commodity (ETC) is a type of security that can offer traders and investors without direct access to spot or derivatives commodities markets exposure to commodities such as metals, energy, and livestock.

How is etc calculated in project management?

There are two ways to calculate ETC:Based on past project performance: ETC = (BAC – EV) / CPI. Each of these input variables (right side of the equation) is normally determined prior to this step: ... Based on a new estimate. This is called a Management ETC.

How do you calculate EV in project management?

The Formula for Earned Value (EV) Take the actual percentage of the completed work and multiply it by the project budget and you will get the Earned Value. Earned Value = % of completed work X BAC (Budget at Completion).

What is the formula for EAC?

When performance is steady and has not deviated too sharply from the original estimate, use the following formula: EAC = BAC/CPI(Estimate at Completion equals Budget at Completion divided by Cost Performance Index).

How do you calculate Estimate to Complete (ETC)?

To do it correctly, it’s not enough to know the formula - you should know what costs should be taken into account so that your estimates are as accurate as possible.

What is ETC in construction?

As you can see, the Estimate to Complete (ETC) is about forecasting how much more money you need to spend in order to complete the project. It doesn’t take into account the actual costs (AC) the project incurred so far. You can’t calculate your project’s Estimate at Completion (EAC) without the ETC.

What does it mean when estimates are more pessimistic than initial?

If Estimations > Allocations in a past project, it means that we were more pessimistic than initially, and the project was delivered with less involvement of our resources.

When forecasting how much money it will cost you to complete a project, can you use two estimates that sound very?

When forecasting how much money it will cost you to complete the project, you can use two estimates that sound very similar but are, in fact, completely different: Estimate to Complete (ETC) and Estimate at Completion (EAC).

What does "estimates allocations" mean?

If Estimates < Allocations in a past or ongoing project, it means that we estimated the project at the beginning incorrectly and overestimated that we’d be able to deliver the project on such an hourly basis.

What is an estimate to complete?

The Estimate To Complete (usually abbreviated ETC) is the remaining cost you expect to pay in order to complete a project.

Why is it important to calculate ETC?

That’s why calculating the ETC and other values multiple times during the project is so important. It helps you instantly pinpoint the moment when your project is running off its course and take action to keep it profitable.

What is ETC in construction?

ETC is a cost estimation for completing the remaining work in a project whereas EAC is as estimation for complete all the work in a project. Both are related to each other by the following formula.

What is ETC in math?

ETC is an estimated cost of remaining work. So, the first step for finding the formulas for ETC is finding a formula for the remaining work.

What does "typical" mean in EVM?

In EVM parlance, we say that the project performance was typical. Typical means that past performance is indicative of the future performance.

Why is ETC important?

ETC is an important EVM parameter. It can be computed either by looking at project’s past performance or by re-evaluating the remaining project work. It changes as the project progresses. It should be periodically revised to accurately reflect current status of a project and forecast what might happen in future.

How many units of money is ETC?

ETC = 46286 units of money (this figure is same as our mathematical calculation)

What is estimate to complete?

Estimate To Complete is an estimation of funds required to complete the remaining work in a project. It is an important Earned Value Management (EVM) metric, which is used for forecasting the money needed for the remaining project work.

Can we use future projected cost efficiency instead of current CPI?

Since we have to determine the expected cost of remaining (future) work, we can should use future projected cost efficiency instead of current CPI in the above expression. We can rewrite the above expression as:

What is ETC in construction?

One such technique is the Estimate to Complete (ETC). This is another forecasting technique, used along with the Estimate at Completion, it gives you the approximate cost required to complete the remaining work.

What is estimate to complete?

The Estimate to Complete is the expected cost required to complete the remaining work of the project. You will use this forecasting tool when the estimate is no longer valid and you need a new estimate for the remainder of the work. This tool is useful whenever the cost baseline deviates. You will use this tool and communicate the information to stakeholders to get the new budget approved.

What is ETC in PMP?

The Estimate to Complete (ETC) tool is essential for the PMP exam. You may see a few questions from this topic on your exam.

What is the formula for ETC?

You use the formula “ETC = (BAC – EV)/CPI” with an assumption that the future cost performance will be same as the current cost performance.

What is the EAC tool?

There is another forecasting tool that is often confused with the Estimate to Complete. This tool is the Estimate at Completion (EAC).

What is ETC in earned value analysis?

In earned value analysis, the Estimate To Complete, usually abbreviated ETC, is the expected remaining cost to complete the project. It is not the final overall project expected budget (that’s the EAC), rather it is the expenditure from now to the end of the project. It does not include what has already been spent.

What is EV in finance?

Earned Value (EV) is the current progress expressed as a task budget.

What are the inputs for standard earned value procedure?

As per standard earned value procedure, we have already determined the inputs: BAC, PV, EV, and AC.

Is ETC necessary in a project?

In these cases a Management ETC (i.e new estimate) is necessary, which is entered into the ETC column. There is nothing wrong with this practice.

What is the difference between estimate to complete and estimate to complete?

The budget is an estimation at the beginning of the project. However, as the project proceeds, there is new information available that might change the total amount of money needed. Estimate at Completion is used for forecasting the amount of money at the end of the project. Estimate to Complete is the amount of money needed to finish the project at any point.

Why is Estimate to Complete important?

The Estimate to Complete and Estimate at Completion become useful tools when there are changes in a project that alter its budget. Both of these are forecasting tools to see how changes impact the final outcome of the project. If there are changes in the budget, then the new change must again be approved using a change order. Once new changes are incorporated, the budget also changes.

How to calculate Estimate to Complete?

The first method to calculate Estimate to Complete is to use bottom-up cost estimation. The bottom-up cost estimation calculates the budget from the bottom, meaning from the lowest-level of the tasks. In this example, the bottom-up cost estimation is $90,000, which is the Estimate to Complete.

How to calculate EAC?

Estimate to Complete (ETC) and Estimate at Completion (EAC) are used for forecasting the impact of changes in terms of amount of money. Estimate at Completion is equal to the budget, which is the amount of money allocated to complete a project. However, if there are changes to the project, then EAC can be calculated by adding all the estimated costs for the tasks. If the budget of a project changes, then a change order needs to be created and approved. Estimate to Complete can be calculated using bottom-up cost estimation, which involves adding all the costs on the tasks remaining. It can also be calculated using the following formula: ETC = EAC - Actual Cost

What is ETC in construction?

Estimate to complete (ETC) is the expected cost required to finish remaining project work. It can be measured at a given point in time for a project or activity.

How to calculate estimate to complete?

In many cases, baseline project estimates are invalidated by cost overruns and new estimates are required. The second, is to use your original estimates adjusted by the percentage completion of your project tasks.

What is ETC in math?

ETC is the cost needed to complete the remaining work. It’s driven by a performance factor or performance index. Putting it into an equation, you get:

What is the difference between ETC and EAC?

ETC is the expected cost to finish the remaining work of the project, whereas EAC is the expected total cost of completing all work for the project. As EAC considers the total expected cost, it is the sum of actual cost incurred so far for the project (AC) and ETC. Putting it into an equation, you get:

What is the equation for EAC?

Again, our equation for EAC is: EAC = AC + ETC.

What is the formula for EAC?

EAC = AC + ETC. This is the main formula for EAC, which is derived from AC and EAC. However, you may come across sources that are confused about EAC. A number of books, articles and journals mention that EAC changes based on certain assumptions. In fact, EAC doesn’t change directly at all on various assumptions.

Does EAC change based on assumptions?

Don’t assume that EAC changes based on certain assumptions. ETC is what actually changes. You need to focus on ETC and how ETC is calculated based on various assumptions; The formula for EAC is “AC + ETC,” and therefore it is EAC which is changing based on ETC because EAC is derived from ETC.

Does ETC change based on EAC?

ETC doesn’t change based on EAC; and. By focusing on ETC and understanding ETC as the division of work remaining with a performance factor, and it is ETC that drives EAC, a PMP® aspirant can easily calculate various formulae related to EAC and ETC. Image resized and cropped.

Does EAC change with performance factor?

Now, let’s review assumptions based on which the performance factor changes. You’ll see that as the performance factor changes ETC, EAC will also change.

image

Estimate to Complete (Etc) in Project Management

Image
PMBOK Guide You can also refer to Max Wideman Glossary to read some other standard definitions of ETC. You can also refer to my other article on EVM definitions. ETC is is used to forecast the money needed for completing the remaining work of a project. Note: EVM helps in measuring current performance a…
See more on pmbypm.com

Estimate to Complete (Etc) Formulas For The PMP Certification Exam

  • ETC is an estimated cost of remaining work. So, the first step for finding the formulas for ETC is finding a formula for the remaining work. The remaining project work can be easily understood by looking at the following figure. The above figure gives us the following formula for the remaining work. Remaining Work = Total Work – Completed Work Since EVM is all about The Monetary Val…
See more on pmbypm.com

Estimate to Complete

  • The main difference between ETC and EAC is that ETC is a cost estimation for completing the remaining work in a project whereas EAC is current cost estimation for completing whole project work. Both are related to each other by the following formula. ETC = (EAC – AC) EAC is projected budget to complete the total project scope. It includes ETC. You ...
See more on pmbypm.com

1.Videos of What Is ETC Estimate

Url:/videos/search?q=what+is+etc+estimate&qpvt=what+is+etc+estimate&FORM=VDRE

12 hours ago WebETC. Estimate-To-Complete + 4 variants. Projection, Management, Cost. Projection, Management, Cost. 1. ETC. Estimate -T d t o - Complet e ion. Projection, Management, …

2.Estimate to Complete (ETC) Definition & Examples

Url:https://www.projectcubicle.com/estimate-to-complete-definition-and-examples/

30 hours ago Web · Estimate to complete (ETC) is the amount of money needed to finish the project at any point. More to the point, estimate at completion is equal to the budget , …

3.Estimate to Complete (ETC) Formulas In Project …

Url:https://www.pmbypm.com/estimate-to-complete-etc-formula/

9 hours ago Web · ETC = estimate at completion – actual cost However, the standard calculation for Estimate at Completion is based on Estimate To Complete, meaning that …

4.Estimate to Complete (ETC) – Another Project …

Url:https://pmstudycircle.com/estimate-to-complete-etc-an-another-project-forecasting-tool/

7 hours ago WebETC “ETC” is another good acronym for this situation. “ETC” means “estimated time of completion,” so it’s valid to use whenever you want to show that something should be …

5.Estimate to Complete (Earned Value Analysis)

Url:https://www.projectengineer.net/estimate-to-complete-earned-value-analysis/

12 hours ago

6.ETC Estimate Abbreviation Meaning - allacronyms.com

Url:https://www.allacronyms.com/ETC/estimate

23 hours ago

7.Estimate at Completion (EAC) vs. Estimate to Complete …

Url:https://study.com/academy/lesson/estimate-at-completion-eac-vs-estimate-to-complete-etc.html

35 hours ago

8.What is Estimate To Complete? - Simplicable

Url:https://simplicable.com/new/estimate-to-complete

8 hours ago

9.PMP® Prep: Calculating EAC and ETC for Forecasting

Url:https://www.mpug.com/pmp-exam-prep-calculating-eac-and-etc-for-forecasting/

20 hours ago

A B C D E F G H I J K L M N O P Q R S T U V W X Y Z 1 2 3 4 5 6 7 8 9